Project: Boston Medical Center Crosstown – Outpatient Pediatrics
Share:
Project

Boston Medical Center Crosstown – Outpatient Pediatrics

Boston Medical Center Crosstown – Outpatient Pediatrics

TOCCI Creates Outpatient Pediatrics Space on the 7th Floor of Boston Medical Center’s Crosstown Building

TOCCI implemented Integrated Project Delivery (IPD) to turn 25,000 sf into 56 exam rooms, 14 consult rooms, 2 infusion bays and administrative offices. 4 of the exam rooms are designed for treatment and testing such as echocardiogram and EEG neurology.

A designated exam room supports a phlebotomy blood draw station and specimen collection requirements.

Crosstown’s new Outpatient Pediatrics floor supports other congruent sub-clinics including Genera + Adolescent Pediatrics, Child Psychology, and STAR Unit.

Location
Boston, MA
Owner
Boston Medical Center
Architect
Tsoi Kobus Design
Crosstown Reimagined

Following Boston Medical Center’s 2018 acquisition of the Crosstown Center, the facility has undergone a phased redevelopment to support the hospital’s expanding outpatient services. This project was part of a 6-year, multi-phased IPD project throughout the majority of the Crosstown building. 

Smart Walls, Healthier Spaces

To help Boston Medical Center deliver compassionate care in a modern, efficient clinic environment, TOCCI integrated modular KI wall systems that sped up construction, improved acoustics, and supported infection control.

25,000 Square Feet
56 Exam Rooms
2 Weeks Ahead of Schedule
IPD: Built on Trust, Delivered Ahead of Schedule

This 7th floor Outpatient Pediatrics Clinic is part of a 6-year, multi-phased project throughout the majority of the Crosstown building and was delivered using Integrated Project Delivery (IPD); a collaborative approach that brought together BMC, TOCCI, Tsoi Kobus Design, and trade partners from the start. By sharing information early and often, the team was able to resolve challenges quickly and avoid costly delays.

Modular wall systems helped compress the construction schedule, but it was the team’s alignment—daily coordination, clear accountability, and mutual trust—that made the difference.

The project was completed two weeks ahead of schedule, with no compromise to quality or patient care.