Tocci Tops Off East Boston’s 88 Wareham Street

After a busy few months, we celebrated 88 Wareham Street’s topping off last week!

The ceremony marked the near completion of steel erection and the hard work of the entire team on this residential project.

Progress on site is moving along smoothly now that the winter weather is mostly behind us. Steel erection will be completed this week and detailing in the coming week. We have poured the slab on decks for levels 2 & 3, and are expecting to pour slabs on 4 & 5 this week. Spray fire proofing has begun on level 2 and exterior framing is planned for the end of the week. Interior framing will begin next week which will allow for MEP trades to begin layout, coring and some select install. the building is scheduled to be weather tight by the end of May.