Project Update: Brookside Square

Share

Time for an update on Brookside Square, a three-story mixed-use development project, located in the West Concord Village District.

The project is currently wrapping up with the tie rebar for the last section of the slab on grade in the parking garage. It is moving along (about halfway through) with the concrete pours for the 1st slab on the deck and the utilities have begun to be installed. The site contractor is currently backfilling along the East portion of the building and is about to begin the installation of catch basins. The project is tracking to start framing the first week in September.

Below are photos from our visit to Brookside Square: