Insight: 1515 Commonwealth Avenue: Engineering a Better Build
Share:
Insight

1515 Commonwealth Avenue: Engineering a Better Build

1515 Commonwealth Avenue: Engineering a Better Build

When market forces threatened the viability of this 252-unit, two-building multifamily development atop Boston’s highest residential point, TOCCI delivered a solution. We collaborated with The Davis Companies and RODE Architects to cut hard costs by 15%—without sacrificing quality or marketability. With our precision-driven 5-step approach and deep integration of DfMA and Target Value Design, we turned challenges into opportunity, helping 1515 Commonwealth Avenue become a standout new address in Brighton.

Client: The Davis Companies
Architect: RODE Architects
Location: Brighton, MA


Challenge: Building Amid Unprecedented Market Challenges

In a volatile market where high interest rates, material cost spikes, and supply chain disruptions put multifamily projects at risk, The Davis Companies turned to TOCCI for a new path forward. 1515 Commonwealth Avenue, positioned at the highest residential point in Boston, needed to meet demanding quality standards and budget constraints while maintaining a competitive edge in the luxury condominium market.


Solution: Project Rescue in Action

1515 Commonwealth Avenue is a direct result of TOCCI’s Project Rescue program — a systematized approach built on two decades of expertise in Integrated Project Delivery (IPD) and Modular Construction. Working closely with the owner and architect, we implemented a 5-step cost engineering strategy that:

  • Reduced hard costs by 15% from an already competitive GMP.
  • Increased the building’s marketability with no compromise to quality or amenities.
  • Delivered $9.4M in value enhancement ideas and $5.2M in buyout savings.

Our 5-Step Plan included:

  • 4.5% Prefix DfMA: Early adoption of Design for Manufacturing and Assembly principles accelerated timelines and reduced waste.
  • 4.5% Target Value Design: Deep collaboration in preconstruction aligned costs with vision.
  • 2.5% Union Support + Clarity: Proactive engagement streamlined labor and avoided costly delays.
  • 2% Tighter Contingencies: Smart forecasting unlocked resources for design features.
  • 1% Negative Allowance for Target Buy: Real-time procurement strategies maximized market opportunities.

Additionally, our on-the-ground and in-the-model team approach uncovered coordination issues early and streamlined field-built work with prefabricated components, leveraging 4D model visualization.

  • Risk Engineering: De-risking design and schedule through early 4D modeling, Design for Manufacturing and Assembly (DfMA), LOD 400 fabrication-ready modeling for MEPFP trades, and TAKT scheduling. This strategy minimizes RFIs, change orders, and unknowns, creating a predictable and efficient path to delivery.
  • Cost Engineering: Crowd-sourcing cost reduction ideas from subcontractors, maximizing subcontractor scope certainty, tightening contingencies, and targeting value through strategic buyouts. At 1515 Commonwealth Avenue, this approach reduced hard costs by 15% while maintaining design quality.
  • Revenue Engineering: Massing optimization and design iteration enhanced building efficiency and increased potential revenue per square foot, ensuring the project’s marketability and financial viability.

Results: A New Era of Urban Living

The topping-off of 1515 Commonwealth Avenue marked more than a construction milestone — it celebrated overcoming market adversity through collaboration, innovation, and precision engineering.

  • Luxury Residences: 102 high-end condominiums with sweeping city views.
  • Exceptional Amenities: Green roofs, two-floor parking garages, a sky deck, fitness center, and a terrace with a putting green.
  • Sustainability: Eco-friendly design integrated throughout the development.
  • Financial Success: Cost-effective delivery without sacrificing design integrity or project goals.
Aerial close-up of a multi-story building under construction, with blue weather barrier wrap installed across sections of the facade alongside completed panel siding and balconies with windows.
Arrows parallax

Infinite possibilities 
in defined spaces

Let’s work together to future-proof your next project to perform and delight.