Team Strategies for Prefabrication
Share
A key principle of lean implementation is to put people first.
That wasn’t lost at the recent BIMForum conference on prefabrication and modularization; each presentation included team strategies to enable prefab efforts.
- Victor Sanvido, a Senior VP at Southland Industries, advised teams to, “make the project more important than the company.” This is similar to Tocci’s “We all work for the project” mantra – when teams work with overall project goals in mind, each firm benefits further.
- DPR Construction created a leadership team of prefabrication naysayers to champion prefabrication. The naysayers initially held prefabrication charrettes to identify opportunities and then followed up with weekly meetings to maintain progress.
- In order to get field input into the system design, many trade contractors and self-performing contractors use trade foremen as detailers.
- The need for a warehouse manager has emerged. Similar to a site superintendent, someone needs to optimize the prefabrication process in the factory.